Bible Study group needs Plumber bid: Work to be completed a.s.a.p (a license plumber):
(Location: commercial warehouse on Grand Ave. between Van Buren - Roosevelt 85007)
Bid: Dig up and replace cast iron with 3" ABS pipe
1. Saw cut asphalt, both sides thirty inches wide sixty five linear feet
2. Dig down approximately 3 to 4 feet to city clay sewer tap a. inspect tap, b. (take pictures of connection for records)
3. Install a new three inch ABS with proper slope from building to sewer tap with a double clean out (bull horns)
a. Take pictures of all pipe and clean out, showing proper installation
4. Backfilled, trench, 6 inch lifts and compact lightly watering to get max compaction to achieve ninety five percent compaction.
5. Not necessary to Include: asphalt to complete.
NOTE: Currently scheduling the utility markers.